AI datacentres plan on-site power stations on huge scale despite climate risks, research reveals

Datacentre developers in the US and Europe are proposing 181GW of on-site gas-fired capacity due to delays in connecting to national grids, nearly four times Great Britain's peak electricity demand.

SourceThe Guardian AIAuthor: Sandra Laville
AI datacentres plan on-site power stations on huge scale despite climate risks, research reveals
Report an error

The correction channel is not available yet. You can copy the article reference below for later.

Correction instructions

Summary only

Under the source content permission, this page provides an editorial summary, key points, and a link to the original article.

Key points and analysis

Article intelligence

ResearchersAdvanced

Key points

  • Planned AI datacentres in the US, UK, and mainland Europe propose 181GW of on-site gas-fired power capacity.
  • Delays in connecting to national electricity grids are driving the move to on-site generation.
  • 181GW is almost four times the total peak electricity demand of Great Britain.
  • On-site gas power raises significant climate concerns.